Project Overview
Performed by REENTEC Energy Genba Group located within the facility Balıkesir, Sivas ve Bergama as part of the project carried out at the manufacturing facilities, REENTEC Energy successfully 3 × 1600 kVA Substations along with the installation of three 1600 kVA substations, the complete electrical infrastructure of the facilities was successfully delivered.
The project included the installation of the substations, MV and LV power distribution systems, electrical panels, cable tray and cabling systems, field installations, power supply connections, as well as testing and commissioning works. All activities were successfully completed in compliance with international quality standards and occupational health and safety regulations, ensuring the facilities' high power demands are met safely, efficiently, and without interruption.
Scope of Work
- Installation of 3 × 1600 kVA Substations
- Installation of MV and LV Power Distribution Systems
- Complete Factory Electrical Infrastructure Works
- Electrical Panel Installation and Connections
- Cable Tray and Cabling Systems
- Machinery and Process Power Supply Connections
- Protection, Control, and Automation Systems
- Electrical Testing, Measurement, and Commissioning Works
- Technical Reporting and System Handover