KOZA Altın İşletmeleri-Ovacık Altın Madeni
Date2015
LocationBergama-İzmir, Turkey
ClientKOZA Altın İşletmeleri
Scope of Work:Industrial Power Systems – Generator and Power Distribution Systems
Project Overview
Located at the KOZA Altın Ovacık Gold Mine, 500 kVA Diesel Generator Systemtechnical support was provided during the inspection, testing, and commissioning of the Automatic Transfer Switch (ATS), LV power distribution panels, and associated auxiliary equipment for the 500 kVA diesel generator system.
The scope of work included functional testing of the generator control system, utility-to-generator transfer mechanism, power circuit breakers, protection devices, and auxiliary control circuits, verifying the system's safe, reliable, and uninterrupted operation.
Scope of Work
- General Technical Inspection of the 500 kVA Diesel Generator System
- Functional Testing of the Generator Control Panel
- Testing of Automatic Transfer Switch (ATS) Transfer Sequences
- Verification of Utility-to-Generator Transfer Functions
- Technical Inspection of LV Power Distribution Panels and Main Circuit Breakers
- Functional Testing of Protection and Control Equipment
- General Inspection of the Fuel System and Auxiliary Equipment
- Completion of System Commissioning and Operational Testing